Project planning: Difference between revisions
Jump to navigation
Jump to search
Line 34: | Line 34: | ||
*System code skeleton created | *System code skeleton created | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
* | *Initial integration tests using skeleton | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
|} | |} | ||
Line 49: | Line 49: | ||
|- | |- | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
* | *Detailed module designs | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
*Module unit tests | |||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
*Integration tests needed for release pass | *Integration tests needed for release pass | ||
*Module code | |||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
*Packaging | *Packaging | ||
*First pre-alpha release | *First pre-alpha release | ||
|} | |} | ||
Revision as of 19:54, 4 May 2007
Schedule
The first release of Thunderforce is planned to occur around mid-August of this year. The details of the plan will work backwards from that release date.
The following table depicts the current schedule for Thunderforce. Note that week 18 is the week beginning on April 30, 2007. Items in the table cells indicate when those activities should be completed by, which can be by the end of the week indicated.
Please note that, as with any open-source software project, this schedule does not constitute any promise of delivery or adherence.
Week 18 | Week 19 | Week 20 | Week 21 | Week 22 | Week 23 | Week 24 | Week 25 |
---|---|---|---|---|---|---|---|
|
|
|
|
|
|
|
Week 26 | Week 27 | Week 28 | Week 29 | Week 30 | Week 31 | Week 32 | Week 33 |
---|---|---|---|---|---|---|---|
|
|
|
|
Sprints
The following lists the focus of each sprint:
- Initial integration test creation and development of base functionality
- Feature development and integration test refinement
- Release finalization and packaging