Project planning: Difference between revisions
Jump to navigation
Jump to search
(Removed the last three weeks) |
No edit summary |
||
Line 55: | Line 55: | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
*Architectural refinement | *Architectural refinement | ||
|} | |} | ||
<br> | <br> | ||
Line 70: | Line 68: | ||
|- | |- | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| | ||
*Module identification | |||
*System code skeleton created | |||
*Initial integration tests for Dreamforce preview release | *Initial integration tests for Dreamforce preview release | ||
|width="12.5%" valign="top"| | |width="12.5%" valign="top"| |
Revision as of 17:08, 21 August 2007
Schedule
The first release of Thunderforce is planned to occur around mid-August of this year. The details of the plan will work backwards from that release date.
The following table depicts the current schedule for Thunderforce. Weeks begin on Mondays in this schedule. Note that week 18 is the week beginning on April 30, 2007. Items in the table cells indicate when those activities should be completed by, which can be by the end of the week indicated.
Please note that, as with any open-source software project, this schedule does not constitute any promise of delivery or adherence.
Week 18 | Week 19 | Week 20 | Week 21 | Week 22 | Week 23 | Week 24 | Week 25 |
---|---|---|---|---|---|---|---|
|
|
|
|
|
Week 26 | Week 27 | Week 28 | Week 29 | Week 30 | Week 31 | Week 32 | Week 33 |
---|---|---|---|---|---|---|---|
|
|
|
Week 34 | Week 35 | Week 36 | Week 37 | Week 38 | Week 39 | Week 40 | Week 41 |
---|---|---|---|---|---|---|---|
|
|
|
Week 42 | Week 43 | Week 44 | Week 45 | Week 46 | Week 47 | Week 48 | Week 49 |
---|---|---|---|---|---|---|---|
|