Schedule

The first release of Thunderforce is planned to occur around mid-August of this year. The details of the plan will work backwards from that release date.

The following table depicts the current schedule for Thunderforce. Weeks begin on Mondays in this schedule. Note that week 18 is the week beginning on April 30, 2007. Items in the table cells indicate when those activities should be completed by, which can be by the end of the week indicated.

Please note that, as with any open-source software project, this schedule does not constitute any promise of delivery or adherence.

Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25
  • Project plan and scope
  • Context diagram
  • Use cases
  • Notional architecture
  • Identification of architectural risks
  • Experiment planning
  • Initial XML user interface language (XUL) files created
  • XUL files tested with Usability Engineering (UE)


Week 26 Week 27 Week 28 Week 29 Week 30 Week 31 Week 32 Week 33
  • Experiment execution
  • Developer on-boarding instructions
  • Architectural refinement
  • Module identification
  • System code skeleton created


Week 34 Week 35 Week 36 Week 37 Week 38 Week 39 Week 40 Week 41
  • Initial integration tests for Dreamforce preview release
  • Module code for Dreamforce complete
  • Integration tests needed for Dreamforce preview release pass
  • Packaging
  • Dreamforce preview
  • Integration tests needed for version 1.0 release


Week 42 Week 43 Week 44 Week 45 Week 46 Week 47 Week 48 Week 49
  • Module code for 1.0
  • Integration tests needed for the 1.0 release pass
  • Packaging
  • Version 1.0 release


Week 50 Week 51 Week 52